- Posts: 1
- Thank you received: 0
Subsystem
- Milka Susan
- Topic Author
- Offline
- New Member
-
Less
More
1 week 3 days ago #584
by Milka Susan
Subsystem was created by Milka Susan
In STAN, I have already created three separate processes (arable land, grassland, and horticulture land) with all their flows and data entered. Can I convert these existing processes into subsystems (or sub‑processes) of a higher‑level ‘agricultural land’ process without having to re‑enter all the flow data?
Please Log in or Create an account to join the conversation.
1 week 3 days ago #585
by adminST
Unfortunately, it is not possible in STAN to combine existing processes into a subsystem. You have to define the desired subsystem first, and then to model everything that is going on inside (sub-processes, additional internal flows).
Please Log in or Create an account to join the conversation.